Performance-Based Planning & Programming


To measure and improve the performance of regional transportation systems across the United States, a national performance-based planning and programming (PBPP) process has been established. PBPP uses federally established performance metrics to provide an ongoing, objective system for evaluating transportation investment and policy decisions.

Why does the CRTPO conduct PBPP?

As the federally-designed MPO for the Charlotte Urban Area, the CRTPO is required by law to conduct performance-based planning for its planning area, including the Moving Ahead for Progress in the 21st Century Act (MAP-21), Fixing America’s Surface Transportation Act (FAST Act), and the Infrastructure Investment and Jobs Act (IIJA).

PBPP is one of several federal requirements to which DOTs, MPOs, and transit agencies must adhere, and provides the following benefits:

  • Improves visibility and transparency of transportation investments
  • Provides an ongoing, objective system for evaluating investment decisions
  • Bolsters collaboration and communication, along with aligning resources
  • Helps CRTPO make better informed decisions about how to invest limited funds

How does the CRTPO measure performance?

As is required by federal law, the CRTPO coordinates with NCDOT and area transit providers to collect, publish, and monitor performance measures (PMs) in five broad areas:

  • PM-1: Traffic Safety
  • PM-2: Infrastructure Condition
  • PM-3: Transportation System Performance
  • TAM: Transit Asset Management
  • PTASP: Public Transportation Agency Safety Plan

The CRTPO regularly collects new targets and prior year performance data from NCDOT and area transit providers. New targets are periodically reviewed by the Technical Coordination Committee and approved by the Board.

Roadway Performance Measures

The current infrastructure bill that has provided roadway performance guidance since 2022, the IIJA, is set to expire in September 2026. The Congressional Committee on Transportation & Infrastructure has begun a process to draft the new Transportation Bill, a process also referred to as “Reauthorization”. The CRTPO refers to the Association of Metropolitan Planning Organizations (AMPO) for guidance as it monitors the new legislation’s potential changes to PBPP.

PM-1: Traffic Safety

PM-1: Traffic Safety

FHWA’s Traffic Safety Measure monitors the frequency of roadway crashes and sets targets towards reducing their occurrence, especially those involving serious injuries and fatalities. Crash rate is reported at occurrence per 100 million vehicle miles traveled (VMT) to help standardize reporting across urban and rural crash contexts. These measures include:

  • Number of fatalities, and rate per 100 million VMT
  • Number of serious injuries, and rate per 100 million VMT
  • Number of non-motorized fatalities and serious injuries

Traffic Safety reporting is federally required by states and MPOs under the Highway Safety Improvement Program (HSIP). The HSIP is a federal-aid funding program intended to achieve a significant reduction in traffic fatalities and serious injuries on all public roads. Safety performance targets are established annually by State DOTs for each safety performance measure and reported to FHWA in the HSIP Annual Report.

MPOs may establish annual targets for each measure by either agreeing to program projects that will support the statewide targets, or setting quantifiable targets for the metropolitan planning area. The CRTPO does not develop its own targets and instead endorses NCDOT’s statewide targets through its TCC and Board.

PM-1 Performance Measure2025 TargetTarget Status2026 TargetChange
2025 to 2026
Number of fatalities1,103.3Not met1,057.0(46.3)
Fatality rate (per 100 million VMT)0.925Not met0.885(0.04)
Number of serious injuries3,204.8Not met3,101.0(103.8)
Serious injury rate (per 100 million VMT)2.675Not met2.59(0.085)
Number of non-motorized fatalities and non-motorized serious injuries434.6Not met418.70(15.9)
Current and Prior Year PM-1 Traffic Safety Targets Table

Attachments
Related Initiatives

Comprehensive Safety Action Plan

With a $3.15 million Safe Streets and Roads for All federal grant award, the CRTPO will develop a Comprehensive Safety Action Plan (CSAP) to identify and prioritize fatal-and-serious injury crash reduction efforts for the Charlotte Urban Area.

The plan will include a methodology for setting CRTPO-specific PM-1 targets to better reflect baseline data and progress in the planning area towards a goal of zero crashes resulting in serious injuries and fatalities.

Logo for the CRTPO's Comprehensive Safety Action Plan, called Safety is Everyone's Business. Logo includes icons of a pedestrian, bus, car, and cyclist.

Strategic Highway Safety Plan

NCDOT develops and seeks to meet its safety targets through the implementation of its Strategic Highway Safety Plan (SHSP), a statewide blueprint for implementing policies and projects that reduce and eliminating serious crashes.

Additional Resources
PM-2: Infrastructure Condition

PM-2: Infrastructure Condition

FHWA’s Infrastructure Condition Measures evaluate the current state-of-good-repair of the Interstate and non-interstate National Highway System (NHS) measured on three key target areas:

  • Percent of Interstate pavements in good, poor condition;
  • Percent of non-Interstate NHS pavements in good, poor condition; and
  • Percent of NHS bridges by deck area classified as in good, poor condition

FHWA established five metrics for measuring pavement condition, including the International Roughness Index (IRI), cracking percent, rutting, faulting, and Present Serviceability Rating (PSR). For each metric, a threshold is used to establish good, fair, or poor condition. A pavement section is rated in good condition if two or three of the applicable metric ratings are good, and in poor condition if two or more applicable metric ratings are poor.

These measures are set, monitored, and reported on by NCDOT with both two-year (mid-period performance) and four-year (full-period performance) targets, established under requirements in FHWA’s Pavement and Bridge Condition Performance Measures Final Rule.

The CRTPO does not develop its own targets and instead reviews and approves mid- and full-period performance reports and targets developed by NCDOT. As shown in the table below, the CRTPO approved the statewide PM2 targets on June 21, 2023, and state performance has improved or stayed the same since 2019.

PM-2 Performance Measure2019 Actual2020 Actual2021 Actual2022 Actual2023 Actual2023 Target
(2-year)
2025 Target
(4-year)
Percent of Interstate pavements in good condition70.3%76.1%75.1%72.3%76.2%60%62%
Percent of Interstate pavements in poor condition0.1%0.2%0.2%0.1%0.2%1.8%1.5%
Percent of non-Interstate NHS pavements in good condition36.6%38.6%34.6%34.7%35.9%30%31%
Percent of non-Interstate NHS pavements in poor condition1.0%0.8%1.2%1.5%1.4%3.5%3%
Percent of NHS bridges (by deck area) in good condition41.0%38.8%43.8%45.9%44.8%38%38%
Percent of NHS bridges (by deck area) in poor condition4.2%3.8%2.9%2.8%3.0%5%5%
Mid- and Full-Year PM-2 Infrastructure Condition Targets Table
Related Initiatives

SAFER Study

The CRTPO was awarded $5 million from the USDOT to conduct mobility audits in historically underserved and transportation disadvantaged communities. The study’s findings will include prioritized projects to contribute towards improved infrastructure condition performance among identified portions of the CRTPO planning area.

CRTPO's SAFER cross-jurisdictional study logo Safety Accessibility Flexibility Equitable Resiliency

Transportation Improvement Program

The Transportation Improvement Program (TIP) identifies the transportation projects and strategies that CRTPO and NCDOT plan to undertake over the next ten years. All projects receiving federal funding must be in the TIP. The TIP is the region’s way of allocating its transportation resources among the various capital and operating needs of the area, based on a clear set of short-term transportation priorities.

Additional Resources
PM-3: System Performance

PM-3: System Performance

FHWA’s System Performance Measure evaluates the efficiency and effectiveness of the movement of people and goods, and the impact of projects funded by the Congestion Mitigation and Air Quality Improvement (CMAQ) program.

PM-3 consists of roadway and freight targets and performance monitoring for:

  • Passenger travel time reliability on and off the National Highway System (NHS)
  • Freight travel time reliability

The CMAQ performance measures apply to states and MPOs with projects financed with CMAQ funds whose boundary contains any part of an air quality nonattainment or maintenance area where air quality fails to meet the National Ambient Air Quality Standards for ozone, carbon monoxide or particulate matter.

The Charlotte urban area is a nonattainment area and receives CMAQ funds to implement projects towards achieving air quality standards, and must set and work towards the following targets:

  • Total Cumulative On-Road Emissions Reduction from CMAQ Projects
  • Annual Hours of Peak Hour Excessive Delay Per Capita (PHED)
  • Percent of Non-Single Occupancy Vehicle Travel (Non-SOV)

These measures are set, monitored, and reported on by NCDOT with some measures having either/or two-year and/or four-year targets, established under requirements in FHWA’s System Performance/Freight/CMAQ Performance Measures Final Rule.

The CRTPO reviews and approves the PM-3 and CMAQ performance reports and targets developed by NCDOT and includes this information in its Metropolitan Transportation Plan with strategies to improve performance, such as the Congestion Management Process. As shown in the table below, NCDOT established statewide PM-3 and CMAQ targets in December 2022 and the CRTPO approved those statewide targets on June 21, 2023.

PM-3 Performance Measure2019 Actual2020 Actual2021 Actual2022 Actual2023 Actual2023 Target
(2-year)
2025 Target
(4-year)
Percent of person-miles on the Interstate system that are reliable88.7%98.2%96.6%95.1%92.2%75%75%
Percent of person-miles on the non-Interstate NHS that are reliable91.8%96.0%95.7%95.1%94.3%70%70%
Truck Travel Time Reliability Index1.431.231.271.331.351.71.7
Annual hours of peak hour excessive delay per capita (PHED)14.8 hrs.7.6 hrs.9.8 hrs.9.3 hrs.13.7 hrs.34 hrs.34 hrs.
CMAQ Performance Measure2019 Actual2020 Actual2021 Actual2022 Actual2023 Actual2023 Target
(2-year)
2025 Target
(4-year)
Percent Non-SOV travel21.6%21.9%25.6%29.2%33.3%21%21%
CMAQ VOC Cumulative Emission Reductions (kg/day)224.353 kg/day224.353 kg/day224.353 kg/day0.034 kg/day0.034 kg/day0.557 kg/day1.114 kg/day
CMAQ NOx Cumulative Emission Reductions (kg/day)674.724 kg/day674.724 kg/day674.724 kg/day0.095 kg/day0.095 kg/day2.229 kg/day4.458 kg/day
Mid- and Full-Year PM-3 and CMAQ System Performance Targets Table
Related Initiatives

Congestion Management Process

The Congestion Management Process (CMP) is a federal requirement that provides accurate information on transportation system performance and assesses alternative strategies for managing congestion in line with the goals of the Comprehensive Transportation Plan and Metropolitan Transportation Plan.


Beyond 77

Beyond 77 was a two-year comprehensive corridor study along Interstate 77 from the state line to Statesville, adopted in January 2022. The study’s ongoing implementation includes strategies to improve congestion and air quality, in support of the region’s PM-3 and CMAQ targets.

Beyond 77 logo
Additional Resources

Transit Performance Measures

TAM: Transit Asset Management

TAM: Transit Asset Management

The Federal Transit Administration (FTA) requires each federally funded transit agency (TA) to monitor and develop strategies to maintain a state of good repair of public transportation assets.

As reflected in FTA’s TAM Final Rule, agencies fulfill this requirement by developing a TAM Plan. TAs with more than 100 buses (Tier I) are required to develop their own TAM plan, whereas smaller (Tier II) providers collaborate with NCDOT to develop a Group TAM Plan. At the maximum extent possible, all parties involved in creating TAM Plans are required to coordinate with the respective MPO.

The CRTPO does not develop its own TAM targets and instead approves the respective information from its planning area TAs:

The CRTPO includes this information in its Metropolitan Transportation Plan to link transit performance management to regional transportation planning goals and objectives.

Rolling Stock

Percentage of vehicles that have met or exceeded their useful life benchmark (ULB) – the expected life cycle or the acceptable period of use in service for a capital asset, as determined by a transit provider/State, or the default benchmark provided by FTA.

Vehicle TypeULBCATS FY 2026 Targets
(% exceeding ULB)
NCDOT FY 2026 Targets
(% exceeding ULB)
Over-the-road Bus14 years17.50%N/A
Bus12 years (CATS)

14 years (NCDOT)
14.90%20%
Cutaway Bus5 years (CATS)

10 years (NCDOT)
30.53%20%
Light Rail30 years0.00%N/A
Mini-van8 yearsN/A20%
Streetcar30 years0.00%N/A
Van5 years (CATS)

8 years (NCDOT)
N/A20%
Asset Category: Rolling Stock Targets Table
Equipment

Percentage of non-revenue vehicles within a particular asset class that have met or exceeded their Useful Life Benchmark (ULB) – the expected life cycle or the acceptable period of use in service for a capital asset, as determined by a transit provider/State, or the default benchmark provided by FTA.

Vehicle TypeULBCATS FY 2026 Targets
(% exceeding ULB)
NCDOT FY 2026 Targets
(% exceeding ULB)
Automobile
(non-revenue)
8 years48.54%20%
Trucks and Other Rubber Tire Vehicles14 years9.80%20%
Steel Wheel Vehicles25 yearsN/AN/A
Asset Category: Equipment Targets Table
Facilities

Percentage of facilities with a condition rating below 3.0 on the FTA Transit Economic Requirements Model (TERM) Scale.

Facility TypeULBCATS FY 2026 Targets
(% exceeding ULB)
NCDOT FY 2026 Targets
(% exceeding ULB)
Administrative and MaintenanceN/A0.00%20%
Passenger and ParkingN/A5.00%20%
Asset Category: Facilities Targets Table

TERM = Transit Economic Requirements Model – FTA’s Capital Needs Analysis Tool used to assess the current physical condition and future investment needs of the nation’s transit assets/operators.  The TERM Scale includes the following ratings:  5 (Excellent), 4 (Good), 3 (Adequate), 2 (Marginal), 1 (Poor). 

Infrastructure

Percentage of track segments with performance restrictions.

Infrastructure TypeCATS FY 2026 Targets
(% of track with performance restrictions)
NCDOT FY 2026 Targets
(% of track with performance restrictions)
Light Rail1.20%N/A
Streetcar Rail1.20%N/A
Asset Category: Infrastructure Targets Table

*Targets established by CATS and NCDOT in 2024. The FY for CATS and NCDOT is July 1 – June 30.

Attachments
TAM Approval YearCRTPO ResolutionsCRTPO Transit Target Memorandums
20262026 CRTPO Resolution2026 CRTPO Transit Targets Memo
Related Initiatives

Transit Providers Work Group

The CRTPO leads a Transit Providers Work Group (TPWG) to convene all area transit providers and discuss MPO and transit coordination topics, including tracking current transit performance and applying for funding towards capital and planning projects to improve performance.


Transportation Improvement Program

The Transportation Improvement Program (TIP) identifies the transportation projects and strategies that CRTPO and NCDOT plan to undertake over the next ten years. All projects receiving federal funding must be in the TIP. The TIP is the region’s way of allocating its transportation resources among the various capital and operating needs of the area, based on a clear set of short-term transportation priorities.

TAM Information for Transit Providers

Click to download the TAM Performance Report Spreadsheet.

CATS and NCDOT (on behalf of ICATS, MTS, and UCT) are annually required to report agency-adopted TAM targets to the CRTPO. Current information about when and how providers are required to share TAM targets is available through the Internal TPWG webpage.

For questions, email Jerrel Leonard, Transit Planner, at jerrel.leonard@charlottenc.gov.

Additional Resources
PTASP: Public Transportation Agency Safety Plan

PTASP: Public Transportation Agency Safety Plan

The FTA requires each federally funded public transportation agency (TA) to monitor and develop strategies for improving transit safety. TAs report safety targets and steps to meet them in a Public Transportation Agency Safety Plan (PTASP), submitted to NCDOT and the FTA.

As reflected in FTA’s PTASP Final Rule, TAs are required to make PTASP targets available to MPOs to aid in regional transportation planning processes. TAs are also required to, at the maximum extent possible, coordinate to develop MPO safety performance targets.

The CRTPO does not develop its own PTASP targets and instead approves the respective information from each planning area TA:

The CRTPO includes this information in its Metropolitan Transportation Plan to link transit performance management to regional transportation planning goals and objectives.

On April 9, 2024, the FTA released its latest transit safety update in the PTASP Final Rule. This updated guidance includes 22 new or updated performance measures, including eight measures for safety risk reduction programs. New targets set as part of this Final Rule update are indicated below.

Major Safety Events

Major Safety Events

Rate of reportable major safety and security events by mode.

ModeCATSICATSMTSUCT*
Demand Response Bus0.300.000.100.87
Fixed Route Bus1.00N/AN/AN/A
Rail1.00N/AN/AN/A
Streetcar4.50N/AN/AN/A
Transit Safety Category: 2026 Major Safety Events Targets Table

*UCT data is reported as rate per total vehicle service miles (VSM), whereas all other providers report on a rate per total vehicle revenue miles (VRM).

Collisions

Collisions

New performance measure introduced with 2024 PTASP Final Rule update.

Rate of all vehicle/vessel accidents in which there is an impact of a transit vehicle/vessel with:

  • Another transit vehicle
  • A non-transit vehicle
  • A fixed object
  • A person(s) (suicide, attempted suicide included)
  • An animal
  • A rail vehicle
  • A vessel
  • A dock
ModeCATSICATSMTSUCT*
Demand Response Bus1.000.000.150.58
Fixed Route Bus1.00N/AN/AN/A
Rail1.00N/AN/AN/A
Streetcar2.00N/AN/AN/A
Transit Safety Category: 2026 Collisions Targets Table

Pedestrian Collisions

New performance measure introduced with 2024 PTASP Final Rule update.

Rate of all collisions between a transit vehicle and a pedestrian.

ModeCATSICATSMTSUCT*
Demand Response Bus0.000.000.000.14
Fixed Route Bus0.00N/AN/AN/A
Rail0.00N/AN/AN/A
Streetcar0.00N/AN/AN/A
Transit Safety Category: 2026 Pedestrian Collisions Targets Table

Vehicular Collisions

New performance measure introduced with 2024 PTASP Final Rule update.

Rate of all collisions between a transit and non-transit vehicle.

ModeCATSICATSMTSUCT*
Demand Response Bus1.001.000.150.43
Fixed Route Bus1.00N/AN/AN/A
Rail1.00N/AN/AN/A
Streetcar2.00N/AN/AN/A
Transit Safety Category: 2026 Vehicular Collisions Targets Table

*UCT data is reported as rate per total vehicle service miles (VSM), whereas all other providers report on a rate per total vehicle revenue miles (VRM).

Injuries & Fatalities

Injuries

Rate of reportable injuries, by mode.

ModeCATSICATSMTSUCT*
Demand Response Bus1.000.000.021.74
Fixed Route Bus1.00N/AN/AN/A
Rail1.00N/AN/AN/A
Streetcar1.00N/AN/AN/A
Transit Safety Category: 2026 Injuries Targets Table

Fatalities

Rate of reportable fatalities, by mode.

ModeCATSICATSMTSUCT*
Demand Response Bus0.000.000.000.00
Fixed Route Bus0.00N/AN/AN/A
Rail0.00N/AN/AN/A
Streetcar0.00N/AN/AN/A
Transit Safety Category: 2026 Fatalities Targets Table

*UCT data is reported as rate per total vehicle service miles (VSM), whereas all other providers report on a rate per total vehicle revenue miles (VRM).

Transit Worker Safety

Transit Worker Injury

New performance measure introduced with 2024 PTASP Final Rule update.

Rate of reportable transit worker injuries – including transit vehicle staff, transit employees and contractors, and other transit staff – by mode.

ModeCATSICATSMTSUCT*
Demand Response Bus1.000.000.020.58
Fixed Route Bus1.00N/AN/AN/A
Rail1.00N/AN/AN/A
Streetcar1.00N/AN/AN/A
Transit Safety Category: 2026 Transit Worker Injury Targets Table

Transit Worker Fatality

New performance measure introduced with 2024 PTASP Final Rule update.

Rate of reportable transit worker fatalities – including transit vehicle staff, transit employees and contractors, and other transit staff – by mode.

ModeCATSICATSMTSUCT*
Demand Response Bus0.000.000.000.00
Fixed Route Bus0.00N/AN/AN/A
Rail0.00N/AN/AN/A
Streetcar0.00N/AN/AN/A
Transit Safety Category: 2026 Transit Worker Fatality Targets Table

Assaults on Transit Workers

New performance measure introduced with 2024 PTASP Final Rule update.

Rate of reportable transit worker fatalities – including on transit vehicle staff, transit employees and contractors, and other transit staff – by mode.

ModeCATSICATSMTSUCT*
Demand Response Bus0.000.000.000.72
Fixed Route Bus0.00N/AN/AN/A
Rail0.00N/AN/AN/A
Streetcar0.00N/AN/AN/A
Transit Safety Category: 2026 Assaults on Transit Workers Targets Table

*UCT data is reported as rate per total vehicle service miles (VSM), whereas all other providers report on a rate per total vehicle revenue miles (VRM).

System Reliability

System Reliability

Mean (or average) distance between major mechanical failures, by mode.

ModeCATSICATSMTSUCT*
Demand Response Bus33,3330.0025,00023,000
Fixed Route Bus10,000N/AN/AN/A
Rail20,000N/AN/AN/A
Streetcar7,000N/AN/AN/A
Transit Safety Category: 2026 System Reliability Targets Table

*UCT data is reported as rate per total vehicle service miles (VSM), whereas all other providers report on a rate per total vehicle revenue miles (VRM).

Attachments
PTASP Approval YearCRTPO ResolutionsCRTPO Transit Target Memorandums
20262026 CRTPO Resolution2026 CRTPO Transit Targets Memo
Related Initiatives

Transit Providers Work Group

The CRTPO leads a Transit Providers Work Group (TPWG) to convene all area transit providers and discuss MPO and transit coordination topics, including tracking current transit performance and applying for funding towards capital and planning projects to improve performance.

PTASP Information for Transit Providers

Click to download the PTASP Performance Report Spreadsheet.

Area transit providers, including CATS, ICATS, MTS, and UCT, are annually required to report agency-adopted PTASP targets to the CRTPO. Current information about when and how providers are required to share PTASP targets is available through the Internal TPWG webpage.

For questions, email Jerrel Leonard, Transit Planner, at jerrel.leonard@charlottenc.gov.

Additional Resources

Non-Federal Key Performance Indicators (KPIs)

The CRTPO may opt to maintain its own Non-Federal KPIs to monitor region-specific priorities like Complete Streets projects and transportation to job access. The CRTPO is undergoing a refresh to identify KPIs and develop associated performance monitoring systems and will have more information on this webpage in mid-2026.

For additional information about the CRTPO’s Performance-Based Planning and Programming practice, contact Will Snyder at will.snyder@charlottenc.gov or send a general inquiry to email@crtpo.org.